The Caraga State University (CSU) – the partner SUC in Caraga — scheduled the PC deployment and installation to all public high school recipients on September 23, 2010 to October 5, 2010.
The process agreed was that AIR21 (the firm who are responsible for the shipping of equipments) will unload immediately the PCs in the 1st school scheduled for the day and to proceed immediately to the 2nd school.
The iSchools Project Manager, Mr. Jaymer Jayoma led the deployment along with his team members namely:
- Mr. Joel Mercado
- Mr. Raffy Tuan
- Mr. Francis Neri
- Mr. Michael Siega, and
- Mr. Louie Jay Bulahan
The following installation schedule was set:
Day 1, October 1, 2010:
· Agusan National High School, Butuan City
· Butuan City Schools of Arts and Trade, Butuan City
· Taligaman National High School
Day 2, October 2, 2010:
· Tinigbasan National High School
· La Union Integrated School
· Balangbalang Integrated High School
Day 3, October 3, 2010:
· Bislig City National High School
· Trento National High School
· Barobo National High School
· San Vincente National High School
Day 4, October 4, 2010:
· Surigao City National High School
· Nueva Estrella National High School
· Capalayan National High School
· Pili National High School
Day 5, October 5, 2010:
· Culit Integrated Secondary School
· Manoligao Integrated Secondary School
· Libertad National High School
The installation team was divided into two groups as:
TEAM 1: Mr. Jaymer Jayoma,
Mr. Louie Jay Bulahan and
Mr. Francis Neri
TEAM 2: Mr. Joel Mercado,
Mr. Raffy Tuan and
Mr. Michael Siega.
Upon installation, there were devices found to be not functional and there’s a need for replacement:
| School | Equipments |
| Agusan NHS Bislig City NHS Trento NHS Capalayan NHS Libertad NHS Barobo NHS | 1 UPS Defective Server’s UPS (No power) 1 PC no power cord 1 PC no memory card 1 keyboard Server’s top fan 1 monitor w/ horizontal line 1 UPS not charging 1 UPS defective |